Thermo-modernization of the complex of buildings in the School of Economics in Tczew, Pomeranian Voivodeship, Poland - ENNEREG Good Practice in Energy Efficient Buildings
The project covers thermo-modernisation of two objects in the School of Economics in Tczew. Estimated energy consumption after thermo-moderniastion will reach 61,8 (toe/year), what means savings of thermal energy at the level 46% annually. Additionally to wall insulation, on a boarding building the solar collectors will be installed The investment results in energy savings of 4,2 (toe/year).
Summary
[EN - English] | Website
Program name: The Pomorski Regional Operational Programme, year 2007-2013
Priority name: Environment and energy friendly to the environment
Aims and Objectives of this Sustainable Energy Action
The project covers thermo-modernisation of two objects in the School of Economics in Tczew.
Estimated energy consumption after thermo-moderniastion will reach 61,8 (toe/year), what means savings of thermal energy at the level 46% annually. Additionally to wall insulation, on a boarding building the solar collectors will be installed The investment results in energy savings of 4,2 (toe/year).
Scope if investment in each building includes the following works:
- School building:
- insulation of external walls
- insulation the roof
- replacement windows
- Building of boarding:
- insulation of external walls
- insulation the roof
- replacement of windows except the kitchen and dining room
- modernization of heating systems
- upgrades of DHW system including installation of solar collectors.
In addition, dissemination/promotion and education campaign for the staff and school energy manager has been run.
Results and Impacts
Project outcomes in terms of ENNEREG’s performance indicators:
- Start Date: 20.12.2010
- End Date: 30.07.2011
Cumulative investment made by stakeholders in sustainable energy (kEuro)
- Renewable energy production: 61,8 (toe/year)
- Primary energy savings – 46%
- Reductions of greenhouse gas emissions: 121,88 t CO2e/year – 48,8%
Cost-benefit analysis:
- Savings 10182 (€/year)
Other relevant project outcomes /impacts:
- education
- solar energy
Technical and Financial Implementation
Value of project: 373 028 28,1 €
The project funded by:
- 50% - European Regional Development Fund – 154 266 €
- 50% - own contribution - 154 266 €
The Partners and Stakeholders
- Staroste of Tczew District – building owner
- BAPE – energy audit
- Designer – Architectural Studio Archi-Cad, Jacek Szczęsny
- Builder - ZUH Sław-Bud, Sławomir Strzałkowski
Lessons Learnt
- Gained experience in raising funds – the first such investment in Tczew Poviat
- Obstructions – too short time to prepare the investment: develope documentation, selection of construction company
- Factors of success – a large mobilization at each stage of preparation and realization of investments by Poviat officers
How this Action could be Replicated
This action could be replicated at the planning and implementation stage of thermomodernization investment: experience gathered how to apply for
financial support, how to organize smooth construction process can be utilized and transferred to other regions.
Related Information on the Regions 202020 Website:
- Sustainable Energy Theme(s): Education and Training : : Sustainable / Energy Efficient Buildings
- Region(s)/Community(ies): PL: Pomerania :
Last updated: 12/12/2011 5:36pm - Contact: Katarzyna GRECKA -